Engineering - Civil Enginnering
You Are Here :: Home > Civil Engineering > Construction Planning and Mgmt-General Questions
19. |
Free float is mainly used to
|
A. |
identify the activities which can be delayed without affecting the total float of preceding activity |
B.
|
identify the activities, which can be delayed without affecting the total float of succeeding activity |
C.
|
establish priorities
|
D.
|
identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
|
|
Answer: Option B
Explanation:
|
20. |
Whenever an activity has zero total float, then
|
A. |
free float of the activity must be zero but independent float need not be zero |
B.
|
independent float must be zero but free float need not be zero |
C.
|
free float and independent float both must be zero
|
D.
|
free float and independent float both need not be zero
|
|
Answer: Option C
Explanation:
|
21. |
Total float for any activity is defined as the difference between
|
A. |
its latest finish time and earliest start time for its successor activity |
B.
|
its latest start time and earliest start time |
C.
|
its latest start time and earliest finish time
|
D.
|
its earliest finish time and earliest start time for its successor activity
|
|
Answer: Option B
Explanation:
|
22. |
In the network shown in Fig. independent float for the activity 3-5 will be (the number on the arrow shows the duration of activity)
|
A. |
0 |
B.
|
1 |
C.
|
2
|
D.
|
none of the above
|
|
Answer: Option B
Explanation:
|
23. |
In the network shown in Fig. , the critical path is
|
A. |
1-2-3-4-5-6 |
B.
|
1-2-4-5-6 |
C.
|
1-2-3-5-6
|
D.
|
1-2-4-3-5-6
|
|
Answer: Option A
Explanation:
|
24. |
Select the incorrect statement.
|
A. |
A critical path always begins at the very first event. |
B.
|
A critical path always terminates at the last event. |
C.
|
Critical activities control the project duration.
|
D.
|
Critical activity is the one for which free float is zero.
|
|
Answer: Option D
Explanation:
|
« prev
next »