Engineering - Construction Planning and Mgmt - Discussion

You Are Here :: Home > Civil Engineering > Construction Planning and Mgmt - Discussion

 



Q.

Total float for any activity is defined as the difference between                         


A. its latest finish time and earliest start time for its successor activity B. its latest start time and earliest start time
C. its latest start time and earliest finish time D. its earliest finish time and earliest start time for its successor activity

Answer: Option B
Explaination:

 


No Explanation




Discussion

Your Comments Goes here...
NameDiscussion