Q.

Select the incorrect statement.                         


A. A critical path always begins at the very first event. B. A critical path always terminates at the last event.
C. Critical activities control the project duration. D. Critical activity is the one for which free float is zero.

Answer: Option D
Explaination:

 


No Explanation