7. |
With reference to the network shown in Fig. , which statement is incorrect ?
|
A. |
Events 3 and 4 occur after event 2. |
B.
|
Event 7 can occur after event 4. |
C.
|
Event 7 precedes event 6.
|
D.
|
Event 5 follows event 3.
|
|
Answer: Option B
Explanation:
|
8. |
In the network shown in Fig., the concurrent and preceding activities corresponding to activity 2-4 are respectively
|
A. |
1-2 and 4-7 |
B.
|
2-3 and 1-2 |
C.
|
2-3 and 4-7
|
D.
|
1-2 and 3-6
|
|
Answer: Option B
Explanation:
|
9. |
Which of the following does not represent an activity?
|
A. |
site located |
B.
|
foundation is being dug |
C.
|
the office area is being cleaned
|
D.
|
the invitations are being sent
|
|
Answer: Option A
Explanation:
|
10. |
Earliest finish of an activity is always
|
A. |
greater than earliest event time of the following node |
B.
|
less than earliest event time of the following node |
C.
|
less than or equal to earliest event time of the following node
|
D.
|
greater than or equal to earliest event time of the following node
|
|
Answer: Option C
Explanation:
|
11. |
Select the incorrect statement.
|
A. |
Earliest start of an activity is the early event time of the node it leaves. |
B.
|
Latest finish of an activity is the late event time of the node it enters. |
C.
|
Latest start of an activity is its latest finish minus its duration.
|
D.
|
none of the above
|
|
Answer: Option D
Explanation:
|
12. |
In the network shown in Fig. the earliest start time of activity 5-6 is (the number on the arrow shows duration of the activity)
|
|
Answer: Option C
Explanation:
|