Select the incorrect statement.                         


A. Earliest start of an activity is the early event time of the node it leaves. B. Latest finish of an activity is the late event time of the node it enters.
C. Latest start of an activity is its latest finish minus its duration. D. none of the above

Answer: Option D
Explaination:

 