In the network shown in Fig., the concurrent and preceding activities corresponding to activity 2-4 are respectively                         


A. 1-2 and 4-7 B. 2-3 and 1-2
C. 2-3 and 4-7 D. 1-2 and 3-6

Answer: Option B
Explaination:

 


No Explanation