Engineering - Civil Enginnering
You Are Here :: Home > Civil Engineering > Construction Planning and Mgmt-General Questions
1. |
PERT technique of network analysis is mainly useful for
|
A. |
small projects |
B.
|
large and complex projects |
C.
|
research and development projects
|
D.
|
deterministic activities
|
|
Answer: Option C
Explanation:
|
2. |
Select the correct statement.
|
A. |
Activity arrows in a CPM network are drawn to scale |
B.
|
The tail of an arrow represents the finish of an activity |
C.
|
Arrow bead represents the start of an activity
|
D.
|
none of the above
|
|
Answer: Option D
Explanation:
|
3. |
Which of the following is a weakness of bar chart ?
|
A. |
interdependencies of activities |
B.
|
project progress |
C.
|
uncertainties
|
D.
|
all of the above
|
|
Answer: Option D
Explanation:
|
4. |
Which of the following is not a PERT event ?
|
A. |
site investigation started |
B.
|
sessional work completed |
C.
|
bus starts from Jaipur
|
D.
|
class is being attended
|
|
Answer: Option D
Explanation:
|
5. |
In PERT analysis, the time estimates of activities and probability of their occurrence follow
|
A. |
normal distribution curve |
B.
|
Poisson's distribution curve |
C.
|
Beta - distribution curve
|
D.
|
none of the above
|
|
Answer: Option C
Explanation:
|
6. |
The area under the Beta - distribution curve is divided into two equal parts by
|
A. |
most likely time |
B.
|
optimistic time |
C.
|
pessimistic time
|
D.
|
expected time
|
|
Answer: Option D
Explanation:
|
next »