Engineering - Civil Enginnering
You Are Here :: Home > Civil Engineering > Highway Engineering-General Questions
55. |
Select the incorrect statement.
|
A. |
Stop or red time of a signal is the sum of go and clearance intervals for the cross flow. |
B.
|
Go or green time of a signal is the sum of stop and clearance intervals for the cross flow. |
C.
|
Clearance time is generally 3 to 5 seconds.
|
D.
|
The cycle length is normally 40 to 60 seconds for two phase signals.
|
|
Answer: Option B
Explanation:
|
56. |
Softening point of bitumen to be used for read construction at a place where maximum temperature is 40° C should be
|
A. |
less-than 40°C |
B.
|
greater than 40°C |
C.
|
equal to 40°C
|
D.
|
none of the above
|
|
Answer: Option B
Explanation:
|
57. |
Stopping sight distance is always
|
A. |
less than overtaking sight distance |
B.
|
equal to overtaking sight distance |
C.
|
more than overtaking sight distance
|
D.
|
none of the above
|
|
Answer: Option A
Explanation:
|
58. |
The absolute minimum radius of curve for safe operation for a speed of 110 kmph is
|
A. |
110 m |
B.
|
220 m |
C.
|
440 m
|
D.
|
577 m
|
|
Answer: Option C
Explanation:
|
59. |
The attainment of super elevation by rotation of pavement about the inner edge of the pavement
|
A. |
is preferable in steep terrain |
B.
|
results in balancing the earthwork |
C.
|
avoids the drainage problem in flat terrain
|
D.
|
does not change the vertical alignment of road
|
|
Answer: Option C
Explanation:
|
60. |
The background colour of the informatory sign board is
|
A. |
red |
B.
|
yellow |
C.
|
green
|
D.
|
white
|
|
Answer: Option B
Explanation:
|