37. |
Slack time refers to
|
A. |
an activity |
B.
|
an event |
C.
|
both event and activity
|
D.
|
none of the above
|
|
Answer: Option B
Explanation:
|
38. |
The normal time required for the comple-tion of project in the above problem is
|
A. |
9 days |
B.
|
13 days |
C.
|
14 days
|
D.
|
19 days
|
|
Answer: Option C
Explanation:
|
39. |
The constraints in case of resource smoothening operation would be
|
A. |
resources |
B.
|
project duration time |
C.
|
both resources and project duration time
|
D.
|
none of the above
|
|
Answer: Option B
Explanation:
|
40. |
Updating may result in
|
A. |
change of critical path |
B.
|
decrease of project completion time |
C.
|
increase of project completion time
|
D.
|
all of the above
|
|
Answer: Option D
Explanation:
|
41. |
Crash project duration is obtained by summing the
|
A. |
normal durations for all the activities |
B.
|
crash durations for all activities |
C.
|
crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities
|
D.
|
crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.
|
|
Answer: Option D
Explanation:
|
42. |
Interfering float is the difference between
|
A. |
total float and free float |
B.
|
total float and independent float |
C.
|
free float and independent float
|
D.
|
none of the above
|
|
Answer: Option A
Explanation:
|