31. |
The time with which direct cost does not reduce with the increase in time is known as
|
A. |
crash time |
B.
|
normal time |
C.
|
optimistic time
|
D.
|
standard time
|
|
Answer: Option B
Explanation:
|
32. |
The time corresponding to minimum total project cost is
|
A. |
crash time |
B.
|
normal time |
C.
|
optimistic time
|
D.
|
between normal time and crash time
|
|
Answer: Option D
Explanation:
|
33. |
The direct cost of a project with respect to normal time is
|
A. |
minimum |
B.
|
maximum |
C.
|
zero
|
D.
|
infinite
|
|
Answer: Option A
Explanation:
|
34. |
The reduction in project time normally results in
|
A. |
decreasing the direct cost and increasing indirect cost |
B.
|
increasing the direct cost and decreasing the indirect cost |
C.
|
increasing the direct cost and indirect cost both
|
D.
|
decreasing the direct cost and indirect cost both
|
|
Answer: Option B
Explanation:
|
35. |
Economic saving of time results by crashing
|
A. |
cheapest critical activity |
B.
|
cheapest non-critical activity |
C.
|
costliest critical activity
|
D.
|
costliest non-critical activity
|
|
Answer: Option A
Explanation:
|
36. |
The process of incorporating changes and rescheduling or replanning is called
|
A. |
resource levelling |
B.
|
resource smoothening |
C.
|
updating
|
D.
|
critical path scheduling
|
|
Answer: Option C
Explanation:
|