The time with which direct cost does not reduce with the increase in time is known as                        


A. crash time B. normal time
C. optimistic time D. standard time




32.

The time corresponding to minimum total project cost is                        


A. crash time B. normal time
C. optimistic time D. between normal time and crash time




33.

The direct cost of a project with respect to normal time is                        


A. minimum B. maximum
C. zero D. infinite




34.

The reduction in project time normally results in                        


A. decreasing the direct cost and increasing indirect cost B. increasing the direct cost and decreasing the indirect cost
C. increasing the direct cost and indirect cost both D. decreasing the direct cost and indirect cost both




35.

Economic saving of time results by crashing                        


A. cheapest critical activity B. cheapest non-critical activity
C. costliest critical activity D. costliest non-critical activity




36.

The process of incorporating changes and rescheduling or replanning is called                        


A. resource levelling B. resource smoothening
C. updating D. critical path scheduling