25.

Free float for any activity is defined as the difference between                        


A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time
C. its latest finish time and earliest start time for its successor activity D. its earliest finish time and latest start time for its successor activity




26.

Critical path                        


A. is always longest B. is always shortest
C. may be longest D. may be shortest




27.

The independent float affects only                        


A. preceding activities B. succeeding activities
C. the particular activity involved D. none of the above




28.

A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be                        


A. 15 minutes B. 20.143 minutes
C. 21 minutes D. 27 minutes




29.

What estimate would you give for the variance in above problem ?                        


A. 81 B. 54
C. 36 D. 9




30.

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as                        


A. total float B. free float
C. interfering float D. independent float