1.

PERT technique of network analysis is mainly useful for                        


A. small projects B. large and complex projects
C. research and development projects D. deterministic activities




2.

Select the correct statement.                        


A. Activity arrows in a CPM network are drawn to scale B. The tail of an arrow represents the finish of an activity
C. Arrow bead represents the start of an activity D. none of the above




3.

Which of the following is a weakness of bar chart ?                        


A. interdependencies of activities B. project progress
C. uncertainties D. all of the above




4.

Which of the following is not a PERT event ?                        


A. site investigation started B. sessional work completed
C. bus starts from Jaipur D. class is being attended




5.

In PERT analysis, the time estimates of activities and probability of their occurrence follow                         


A. normal distribution curve B. Poisson's distribution curve
C. Beta - distribution curve D. none of the above




6.

The area under the Beta - distribution curve is divided into two equal parts by                        


A. most likely time B. optimistic time
C. pessimistic time D. expected time