55. |
PERT has following time estimate
|
A. |
one time estimate |
B.
|
two time estimate |
C.
|
three time estimate
|
D.
|
four time estimate
|
|
Answer: Option C
Explanation:
|
56. |
Pick up the incorrect statement about advantages of work sampling
|
A. |
permits a fine breakdown of activities and delays |
B.
|
simultaneous study of many operators may be made by a single observer |
C.
|
calculations are easier, method is economical and less time consuming
|
D.
|
no time measuring devices are generally needed
|
|
Answer: Option A
Explanation:
|
57. |
Process layout is employed for
|
A. |
batch production |
B.
|
continuous type of product |
C.
|
effective utilization of machines
|
D.
|
all of the above
|
|
Answer: Option A
Explanation:
|
58. |
Product layout is employed for
|
A. |
batch production |
B.
|
continuous production1 |
C.
|
effective utilisation of machine
|
D.
|
all of the above
|
|
Answer: Option B
Explanation:
|
59. |
Queuing theory deals with problems of
|
A. |
material handling |
B.
|
reducing the waiting time or idle Jajme |
C.
|
better utilization of man services
|
D.
|
effective use of machines
|
|
Answer: Option B
Explanation:
|
60. |
Routing is essential in the following type of industry
|
A. |
assembly industry |
B.
|
process industry |
C.
|
job order industry
|
D.
|
mass production industry
|
|
Answer: Option A
Explanation:
|