43. |
Routing prescribes the
|
A. |
flow oftnaterial in the plant |
B.
|
proper utilization of man power |
C.
|
proper utilization of machines
|
D.
|
inspection of final product
|
|
Answer: Option A
Explanation:
|
44. |
Scheduling gives information about
|
A. |
when work should start and how much work should be completed during a certain period |
B.
|
when work should complete |
C.
|
that how idle time can be minimised
|
D.
|
prcper utilisation of machines
|
|
Answer: Option A
Explanation:
|
45. |
Standard time as compared to normal time is
|
A. |
greater |
B.
|
smaller |
C.
|
equal
|
D.
|
there is no such correlation
|
|
Answer: Option A
Explanation:
|
46. |
Standard time is defined as
|
A. |
normal time + allowances |
B.
|
normal time + idle time + allowances |
C.
|
normal time + idle time
|
D.
|
only normal time for an operation
|
|
Answer: Option A
Explanation:
|
47. |
Standing orders which are statutory are applicable to
|
A. |
all industries |
B.
|
all process industries and thermal power plants |
C.
|
only major industries
|
D.
|
only key industries
|
|
Answer: Option E
Explanation:
|
48. |
Statistical quality control techniques are based on the theory of
|
A. |
quality |
B.
|
statistics |
C.
|
probability
|
D.
|
all of the above
|
|
Answer: Option C
Explanation:
|
« prev
next »