Consider the following situations.
1.Soil is soft.
2.Volume of existing surface traffic on the alignment is heavy.
3.Track is at a deeper level.
4.Water table is high.
In the construction of Metro Railways, "Cut and Cover" method of construction is suitable in situations listed at                         


A. 1 and 2 B. 1 and 3
C. 1 and 4 D. 2 and 3

Answer: Option C