Q.

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively                         


A. 3.5 and 5/6 B. 5 and 25/36
C. 3.5 and 25/36 D. 4 and 5/6

Answer: Option C
Explaination:

 


No Explanation