Q.

In the network shown in Fig. , the activity 6-8 can be started only when                         


A. activity 4—6 is completed B. activity 3 - 5 is completed
C. activity 2—3 is completed D. both activities 2—3 and 4—6 are completed

Answer: Option D
Explaination:

 


No Explanation