Q.

Assertion (A): Activity 5-7 is critical.
Reason (R) : Earliest finish time and latest finish time for events 5-7 are same
Select the correct answer.                         


A. A is correct but R is not correct B. R is correct but A is not correct
C. both A and R are correct D. both A and R are incorrect

Answer: Option A
Explaination:

 


No Explanation