Q.

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days. in how many days can b alone complete that work?                         


A. A. 1/3 days B. B. 1/6 days
C. C. 1/9 days D. D. 1/12 days

Answer: Option B
Explaination:

 