Q.

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?                         


A. 60/11 B. 61/11
C. 71/11 D. 72/11

Answer: Option A
Explaination:

 