If A can do a work in 12 days, B can do it in 18 days and C in 24 days. All the three started the work. A left after two days and C left three days before the completion of the work. How many days are required to complete the work?                         


A. 64 / 7 days B. 69 / 7 days
C. 79 / 7 days D. 89 / 7 days

Answer: Option B
Explaination:

 